October 2026: About 85% complete, opening targeted for December
Construction at Frederick Self Storage is about 85% complete. The base paving for the parking lots and drive lanes went down on September 16 and 17 and passed all testing. Sprinklers are in on the first two floors, the office drywall and restroom tile are done, and the exterior roll-up doors are installed. Crews are now working on the elevators, the exterior finish and the office storefront.
In October the team will finish the exterior on the east and north sides, install sprinklers on the third floor, complete mechanical work and the electrical inspection, put up the building and monument signs, paint, and finish and inspect the elevators. Perimeter fencing and the final sprinkler and plumbing inspections follow in late October and early November, then landscaping and the building and fire alarm finals in November and December. The certificate of occupancy is targeted for December 10, 2026, followed by opening and lease-up.